Out-of-hours working can keep essential facilities running.
Careful overnight planning enabled a significant refurbishment to be completed without taking the hotel's kitchen out of service.
Coordinated sequencing makes restricted working windows manageable.
Strategically managing the strip-out, ceiling installation, and electrical works enabled each stage to be completed and the kitchen handed back ready for use every morning.
The right specification matters in demanding environments.
Washable ceiling tiles and upgraded lighting provided a practical, durable finish better suited to the needs of a busy commercial kitchen.